Slope Protection Drill Site Saudi Aramco Dhahran
Slope Protection Drill Site Saudi Aramco Dhahran
Slope Protection Drill Site Saudi Aramco, Dhahran
Location
Saudi Aramco
Date
May 6
th
, 2017
Materials Used
Hydro CC5
TM
Bulk Rolls
Area
2250 SQM
Project Walkthrough
1. Completed installation on first slope - CCH captured within anchor trench
2. Deployment of CCH on ground below slopes
3. Thermal welding of CCH layers for impermeable joints
4. Hydration of CCH was carried out twice with 2 hour interval
5.Completed installation
6. CCH installed around outflow pipes
7.The installation was carried out in just four days