Construction of Pyrophoric Treatment Area
Construction of Pyrophoric Treatment Area
Construction of Pyrophoric Treatment Area Saudi Aramco, Shaybah
Location
Saudi Aramco Shaybah, NGL Plant
Date
15
th
September, 2020
Materials Used
CCH8™ Bulk Rolls
Area
950 SQM
Project Walkthrough
1. Barricading the Work Area
2. Backfilling of First Layer of Marl
3. Watering First Layer of Marl
4. Third Party Compaction Testing of First Layer of Marl
5. Backfilling of Second Layer of Marl
6. Watering Second Layer of Marl
7. Compaction of Second Layer of Marl
8. Third Party Compaction Testing of Second Layer of Marl
9. Preparation of Dykes
10. Completed Dykes and Final Finishing
11. Deployment of Geotextile Over Dykes and Base Area
12. Laying of Concrete Canvas Over Dykes and Base Area
13. Welding Adjoining Layers of Concrete Canvas (CC)
14. Hydration of Concrete Canvas
15. Deployment of Geotextile Over Base Area
16. Application of Interlock at the Base Area and Dykes
17. Installation of Barricades on the Floor Area
18. Installation of Fence
19. Completed Pyrophoric Treatment Area